Delivery Performance

Delivery Performance

Delivery Performance (DP) is a broadly used standard KPI measurement in supply chains to measure the fulfillment of a customers demand to the wish date. Following the nomenclature of the DR-DP-Matrix three main approaches to measure DR can be distinguished:

  • DP_{T}^{V}
  • DP_{S}^{D}
  • DP_{S}^{T}
Type of measurement: volume (V)/singular(S)
Type of view: on time (T)/ delivery (D)

Contents

Volume/On Time

Formula

If ((Demandp,c + Backlogp − 1,c) > 0)

DP_{T}^{V} = \frac{Delivered_{p,c} + Predelivery_{p-1,c}}{Demand_{p,c} + Backlog_{p-1,c}}

Else

NULL

Demand:= customers wish c:= product identifier p:= Time period e.g. a day, a week, a month ...

The cumulation over a period and a group of product identifiers c is done as follows: DP_{p,c} = \frac{\sum_{p,c}(DP_{T}^{V})}{count_{p,c}(DP_{T}^{V}<>NULL)}

whereas p is determined by demand period

Singular/Delivery and Singular/On Time

Singular case definition

To fit to the needs of the environment, the granularity of a singular case (DP_{*}^{S}) has to be defined. In general a singular case is described by a n-Tupel consisting of a set of the following order and delivery details:

  • order number
  • customer identifier
  • product identifier
  • wish date of customer
  • confirmed date of supplier
  • ship to information
  • delivery date
  • delivery note number

Formula

  • DP_{S}^{D}
After a singular case has been delivered to the customer its DP is measured as follows:
If (wish date = arrival date) then
DPsingular case=1
else
DPsingular case=0

arrival date = delivery date + transit time

By cumulating the results of singular cases over a certain period p and, if necessary, additional criteria c (e.g. customer, product, ...) the delivery performance is calculated as follows:

DP_{p,c} = \frac{\sum_{p,c}(DP)}{count_{p,c}(singular cases)}

whereas p is determined by the arrival date

  • DP_{S}^{T}
After a period has elapsed all singular cases with wish date within period are considered and their DP is measured as follows:
If (wish date = arrival date) then
DRsingular case=1
else
DRsingular case=0

arrival date = delivery date + transit time

By cumulating the results of singular cases over a certain period p and, if necessary, additional criteria c (e.g. customer, product, ...) the delivery performance is calculated as follows:

DP_{p,c} = \frac{\sum_{p,c}(DP)}{count_{p,c}(singular cases)}

whereas p is determined by the first confirmed date

Result

0%≤DP_{T/D}^{S/V}≤100%


Wikimedia Foundation. 2010.

Игры ⚽ Поможем написать курсовую

Look at other dictionaries:

  • Delivery (band) — Delivery was a British blues/progressive rock musical group, formed in the late 1960s. The band was one of the wellsprings of the progressive rock Canterbury scene. Founded in 1966 as Bruno s Blues Band by guitarist Phil Miller, his elder brother …   Wikipedia

  • Delivery (song) — Delivery Single by Babyshambles from the album Shotter s Nation Released …   Wikipedia

  • Delivery schedule adherence — (DSA) is a business metric used to calculate the timeliness of deliveries from suppliers. It is a commonly used supply chain metric and forms part of the Quality, Cost, Delivery group of performance indicators. Calculation Delivery schedule… …   Wikipedia

  • Delivery (chanson) — Delivery Single par Babyshambles extrait de l’album Shotter s Nation Sortie 17 septembre 2007 Enregistrement 2007 Durée …   Wikipédia en Français

  • Performance management — is closely connected to Performance measurement. They are sometimes mistaken for each other. In careful usage, Performance Management is the larger domain and includes Performance Measurement as a component.Performance measurement is the process… …   Wikipedia

  • Performance transformation — Performance Transformation,or Transformation of Performance, is an Outcome, a result, of actions by an individual, a group or an organisation, to radically Make Different the results they achieve.OverviewIn a Business context, Performance… …   Wikipedia

  • performance contract — ➔ contract1 * * * performance contract UK US noun [C] ► HR, LAW a legal agreement in which one organization agrees to pay another when they successfully finish the project or task they were employed to do: »The street lighting service is… …   Financial and business terms

  • performance contracting — performance contract UK US noun [C] ► HR, LAW a legal agreement in which one organization agrees to pay another when they successfully finish the project or task they were employed to do: »The street lighting service is delivered through a… …   Financial and business terms

  • performance measurement — The process of (a) developing indicators to assess progress towards certain predefined goals and (b) reviewing performance against these measures. Performance measures can be applied to the whole organization or to particular departments,… …   Big dictionary of business and management

  • performance measurement — The process of (a) developing indicators to assess progress towards certain predefined goals and (b) reviewing performance against these measures. Performance measures can be applied to the whole organization or to particular departments,… …   Accounting dictionary

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”