Design Assist is the procurement method by which, prior to completion of design, a construction contract may be awarded on a best value basis pursuant to which a contractor provides design assistance to the architect or engineer of record through a design professional separately retained by the contractor.

Design Assist Professional

The Design Assist Professional must be a licensed Professional Engineer. The role of the Design Assist professional (DAP) is to be a Professional Engineering representative of the installing contractor (IC) throughout the entire project, from design through construction. The (DAP) becomes an integral active member of the design team and is the installing contractors link into the design process. The DAP must be a Professional Engineer with specific experience in the area of design and construction related to the systems offering assistance. The (DAP) must have experience in the design process and in the preparation of construction documents. It is imperative that the (DAP) understand the intent of the system design, the project factors, and the decisions that are influencing the system design as created by the Engineer of record (EOR). The (DAP) involvement begins at the SD phase of the project and shall be an active participate in all design charrettes and design team meetings. The DAP will involve the means and method, cost estimating, and scheduling experts of the (IC) in the appropriate design meetings. The DAP shall represent the (IC) in the project construction phase design meetings, and shall be an active participant in these meetings. The DAP shall convey to the (IC) construction team the results and the intent of the decisions made in all the design meetings. The following is general lists of tasks for each specific DAP during the design phase and construction phase of the project:

  1. Plumbing & Fire Protection (DAP)
    1. SD PHASE
      1. Review and comment on the general design approach taken by the Engineer of Record (EOR)
      2. Review and comment on site utilities and site located equipment
      3. Review and comment on (EOR) mechanical room layout
      4. Review and comment on equipment selection by (EOR)
      5. Assist the (EOR) in the establishment of mechanical shaft sizes and locations
      6. Review and comment on special equipment (medical, waste, pure water, etc..) location and sizing as provided by (EOR)
      7. Provide system cost estimate based on (EOR) SD drawings with the appropriate contingencies
    2. DD PHASE
      1. Provide a coordinated mechanical room layout drawings in REVIT based on final equipment selection and location provided by Engineer of record (EOR)
      2. Provide a coordinated special equipment system drawings in REVIT base on the special equipment location provided by Engineer of record (EOR)
      3. Provide installation sequencing and methods description
      4. Provide coordinated mechanical shaft drawings in REVIT indicating all piping, structure, and utilities
      5. Provide coordinated above ceiling drawings in REVIT for all gas, fire protection, sanitary, storm, water, and specialty systems piping based on routing, location, and sizing provided by (EOR)
      6. Provided coordinated floor and roof penetration drawings based on final equipment selection and location provided by (EOR).
      7. Provide system cost estimate with appropriate contingencies
      8. Review and comment on specifications provided by EOR.
      9. Provide final coordinated drawings of underground utilities, roof, floor and wall sleeve location.
    3. CD PHASE
      1. Provide final coordination drawings of the entire system based on (EOR) CD drawings
      2. Provide equipment submittals
      3. Provide system GMP with appropriate contingencies
      4. Provide project schedule with equipment sequencing
      5. Submit fire protection drawings as provided by (EOR) to the fire protection design assist partner.
    4. CA PHASE
      1. Attend and actively participate in all Owner Architect Meetings (OAM)
      2. Provide weekly updated coordination drawings of the entire system based on changes to the (EOR) CD drawings.
      3. Provide weekly updates relative to equipment submittal and delivery information
      4. Provide weekly updates on schedule and changes to the GMP
      5. Update status of construction open issues log
      6. Offer proposed solutions to problems identified in the field
  2. HVAC (DAP)
    1. SD PHASE
      1. Review and comment on the general design approach taken by the Engineer of Record (EOR)
      2. Review and comment on (EOR) mechanical room layout
      3. Review and comment on equipment selection by (EOR)
      4. Assist the (EOR) in the establishment of mechanical shaft sizes and locations
      5. Review and comment on temperature control strategies established by (EOR)
      6. Provide system cost estimate based on (EOR) SD drawings with the appropriate contingencies
    2. DD PHASE
      1. Provide a coordinated mechanical room layout drawings in REVIT based on final equipment selection and location provided by Engineer of record (EOR)
      2. Provide installation sequencing and methods description
      3. Provide coordinated mechanical shaft drawings in REVIT indicating all ductwork, structure, and utilities
      4. Provide coordinated above ceiling drawings in REVIT for all main duct run and equipment based on routing, location, and sizing provided by (EOR)
      5. Provide Temperature control P&ID based on strategies provided by (EOR)
      6. Provided coordinated floor and roof penetration drawings based on final equipment selection and location provided by (EOR).
      7. Provide system cost estimate with appropriate contingencies
      8. Review and comment on specifications provided by EOR.
      9. Provide final coordinated drawings of underground utilities, roof, floor and wall sleeve location.
    3. CD PHASE
      1. Provide final coordination drawings of the entire system based on (EOR) CD drawings
      2. Provide equipment submittals
      3. Provide system GMP with appropriate contingencies
      4. Provide project schedule with equipment sequencing
    4. CA PHASE
      1. Attend and actively participate in all Owner Architect Meetings (OAM)
      2. Provide weekly updated coordination drawings of the entire system based on changes to the (EOR) CD drawings.
      3. Provide weekly updates relative to equipment submittal and delivery information
      4. Provide weekly updates on schedule and changes to the GMP
      5. Update status of construction open issues log
      6. Offer proposed solutions to problems identified in the field
  3. Electrical (DAP)
    1. SD PHASE
      1. Review and comment on the general design approach taken by the Engineer of Record (EOR)
      2. Review and comment on utility power, voice, and data services provided to the facility as indicated by the (EOR)
      3. Assist the (EOR) in the establishment of electrical rooms sizes and locations
      4. Review and comment on (EOR) Electrical room layout
      5. Review and comment on equipment selection by (EOR)
      6. Review and comment on normal and emergency power distribution system design by(EOR)
      7. Review and comment on lighting fixtures as defined by the (EOR)
      8. Review and comment on special systems (nurse call, fire alarm, security, etc..) as defined by the (EOR)
      9. Review and comment on the emergency generator and UPS plant as designed by the (EOR)
      10. Provide system cost estimate based on (EOR) SD drawings with the appropriate contingencies
    2. DD PHASE
      1. Provide a coordinated electrical room layout drawings in REVIT based on final equipment selection and location provided by Engineer of record (EOR)
      2. Provide installation sequencing and methods description
      3. Provide coordinated electrical distribution riser drawings in REVIT indicating all buss duct, conduits, structure, and utilities
      4. Provide coordinated above ceiling drawings in REVIT for all main electrical conduit runs and equipment based on routing, location, and sizing provided by (EOR)
      5. Review and comment on the normal and emergency single line diagrams as provided by the (EOR)
      6. Review and comment on special systems auxiliary equipment room sizes and locations as defined by the (EOR)
      7. Provided coordinated floor penetration drawings based on final equipment selection and location provided by (EOR).
      8. Provide system cost estimate with appropriate contingencies
      9. Review and comment on specifications provided by EOR.
      10. Provide final coordinated drawings of underground utilities, roof, floor and wall sleeve location.
    3. CD PHASE
      1. Provide final coordination drawings of the entire system based on (EOR) CD drawings
      2. Provide equipment submittals
      3. Provide selective coordination for power equipment
      4. Provide project schedule with equipment sequencing
      5. Submit fire alarm drawings to the fire alarm vender
      6. Provide system GMP with appropriate contingencies
    4. CA PHASE
      1. Attend and actively participate in all Owner Architect Meetings (OAM)
      2. Provide weekly updated coordination drawings of the entire system based on changes to the (EOR) CD drawings.
      3. Provide weekly updates relative to equipment submittal and delivery information
      4. Provide weekly updates on schedule and changes to the GMP
      5. Update status of construction open issues log
      6. Offer proposed design solutions to problems identified in the field

References


Wikimedia Foundation. 2010.

Игры ⚽ Поможем написать реферат

Look at other dictionaries:

  • Design U — Genre Design Created by Tim Alp Starring Maureen Ross Neilson, Ernst Hupel, Melanie Martin, Baron Bryant, Christina Maureen Rice, William Mood, Blair Varden, Penny Southam, Ramón Robleto, Tyler Hamilton, Jeff Palmer, Lucie Soulard Theme music… …   Wikipedia

  • Design-bid-build — (or design/bid/build, and abbreviated D B B or D/B/B accordingly), also known as Design tender (or design/tender ), is a project delivery method in which the agency or owner contracts with separate entities for each the design and construction of …   Wikipedia

  • Design–bid–build — (or design/bid/build, and abbreviated D–B–B or D/B/B accordingly), also known as Design–tender (or design/tender ) and traditional method, is a project delivery method in which the agency or owner contracts with separate entities for each the… …   Wikipedia

  • Design for the Environment — Program (DfE) is a United States Environmental Protection Agency (USEPA) program, created in 1992, that works to prevent pollution, and the risk pollution presents to humans and the environment.[1] The EPA DfE program provides information… …   Wikipedia

  • Design for Environment — (DfE) is a general concept that refers to a variety of design approaches that attempt to reduce the overall environmental impact of a product, process or service, where environmental impacts are considered across its life cycle. A type of design… …   Wikipedia

  • CSCL Instructional Design and Tools — Design of Computer Supported Collaborative Learning Environments=Amanda Hefner, Ching O Hsin, Michael Ota and Amy PrescottUniversity of Texas at AustinInstructional Design of CSCLThe design of Computer Supported Collaborative Learning (CSCL) may… …   Wikipedia

  • Ventricular assist device — Graphic describing a Left Ventricular Assist Device (LVAD). The device pumps blood from the left ventricle to the aorta. A Ventricular assist device, or VAD, is a mechanical circulatory device that is used to partially or completely replace the… …   Wikipedia

  • Instructional design — is the practice of creating instructional tools and content to help facilitate learning most effectively. The process consists broadly of determining the current state and needs of the learner, defining the end goal of instruction, and creating… …   Wikipedia

  • Forward assist — The forward assist on a rifle is a button, found commonly on M16 and AR 15 styled rifles, usually located near the bolt closure, that when hit will push the bolt carrier forward, ensuring that the bolt is locked. In order to ensure that the… …   Wikipedia

  • Space Shuttle design process — See also Space Shuttle program Conception and development North American Rockwell Shuttle, 1969 Even before the Apollo moon landing in 1969, in October 1968, NASA began early studies of space shuttle designs. The early studies were denoted Phase… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”