Managing Stage Boundaries (SB)

Managing Stage Boundaries (SB)

Managing Stage Boundaries is one of eight processes that make up PRINCE2, a systematic approach to project management developed by the UK's Office of Government Commerce and used widely in UK government and industry. The fundamental principle of Managing Stage Boundaries (SB) is to ensure that, at the end of each stage, the project stays focused on delivering business benefit.

Description

Managing Stage Boundaries (SB) is one of eight processes outlined by PRINCE2. It is a decision point in the continuity of the project, from which the project will be either continued as planned, adjusted or stopped. The process involves reviewing the current stage, preparing for the next one, and selecting information which can be of use later in the project.

The process is managed by the Project Manager, who informs the Project Board of the likelihood of success in attaining the project's business objective, project plan, together with associated risks and issues. If the Project Board is satisfied with the current stage end and the next stage plan, the project is permitted to continue. Managing Stage Boundaries is therefore a vital process in the management of the project.The objectives of the process are:
* To prove to the Project Board that all the products in the current stage are included and defined
* To provide the information required by the Project Board to assess if the project is still viable
* To obtain authorisation, and margins of tolerance, for the next stage
* To record any information or lessons which might be useful in later stages in or other projects

The products of the process (outputs) are:
* Current Plan actuals, used for showing the improvements from the original Stage Plan. The Stage Plan represents the basis of the Project Manager's day-to-day control and identifies in detail key deliverables, resource requirements and the total cost.
* Next Stage Plan, which represents the actual information stage with added facts and information, and forms part of the Project Board's assessment criteria for continuation of the project.
* Revised Project Plan. The Project Plan gives an overview of the total project, identifies key deliverables, resource requirements, the total cost, and major control points within the project, such as stage boundaries. It is used by the Project Board to measure the progress made and is revised and updated to reflect the latest understanding of the project.
* Updated Risk Log, provides identification, estimation, impact evaluation and countermeasures for all risks of the project. It is created during the start-up and developed during the life of the project and is used by the Project Board to check the viability of the project.
* Revised Business case. The Business Case is a part of the project mandate and is produced before the project is initiated. It includes the reasons for the project, expected business benefits, expected costs and expected risks. The on-going viability of the project is monitored by the Project Board against this Business Case, which is updated with any new changes.
* Lessons Learned Report, describing lessons learned from any events occurring in each stage.
* Revised Project Management Team List This team comprises the entire management structure of Project Board, project manager, plus any Team Managers and project assurance roles. The team is checked and changes are updated if there are any.
* End Stage Report, given by the Project Manager to the Project Board and containing the results achieved during the stage.

References

* Office of Government Commerce (2005), Managing Successful Projects with PRINCE2 (PRINCE2 Manual), The Stationary Office, (Official PRINCE2 publication), which represented the main inspiration.
* Newman, Pippa (1997), Professionalism in Project Management (Digest No: 1997/373), PRINCE2 [project management method] , pages 1-2
* Bradley, Ken (2002), Passing the PRINCE2 examinations, London: The Stationery Office

External links

* [http://www.org.uk/web/site/home/home.asp APM Group]
* [http://www.projectmanagement.net.au/managing_stage_boundaries_sb Managing Stage Boundaries]
* [http://www.prince2.org.uk The APM Group PRINCE2 site - contains list of Accredited Training Organisations]
* [http://www.ogc.gov.uk/prince2/, Official Prince2 website by OGC]
* [http://www.ogc.gov.uk/prince2/downloads/view.htm templates] from the OGC
* [http://www.projectperformance.co.uk/tour/prince2_process_6.php Summary of how this process fits into PRINCE2]


Wikimedia Foundation. 2010.

Игры ⚽ Нужна курсовая?

Look at other dictionaries:

  • Managing stage boundaries — is one of eight processes that make up PRINCE2, a systematic approach to project management developed by the UK s Office of Government Commerce and used widely in UK government and industry. The fundamental principle of Managing Stage Boundaries… …   Wikipedia

  • PRINCE2 — PRojects IN Controlled Environments 2 (PRINCE2) is a structured project management method endorsed by the UK government as the project management standard for public projects. The methodology encompasses the management, control and organisation… …   Wikipedia

  • Projects in Controlled Environments — PRINCE2 (Projects in Controlled Environments) ist eine Projektmanagement Methode. Sie behandelt Management, Steuerung und Organisation eines Projekts. Diagramm zu den PRINCE2 Prozessen. Die Pfeile symbolisieren Informationsflüsse.… …   Deutsch Wikipedia

  • Product software implementation method — A product software implementation method is a systematically structured approach to effectively integrate a software based service or component into the workflow of an organizational structure or an individual end user.This entry focuses on the… …   Wikipedia

  • Product based planning — is mandated for PRINCE2 projects and is a method of identifying all of the products and associated work required to complete a project.DescriptionProduct based planning is intended to ensure that all of the necessary products that will go towards …   Wikipedia

  • Process-data diagram — A process data diagram is a diagram that describes processes and data that act as output of these processes. On the left side the meta process model can be viewed and on the right side the meta concept model can be viewed. A process data diagram… …   Wikipedia

  • Contributors — ▪ 2000       Adams, Andy. Editor and Publisher, Sumo World. Author of Sumo; Sumo World Record Book. • sports and games: Judo; Wrestling: Sumo       Ahn, Ki suk. Assistant Editor, Shindonga of Donga Ilbo. • biographies (in part)       Alder,… …   Universalium

  • France — /frans, frahns/; Fr. /frddahonns/, n. 1. Anatole /ann nann tawl /, (Jacques Anatole Thibault), 1844 1924, French novelist and essayist: Nobel prize 1921. 2. a republic in W Europe. 58,470,421; 212,736 sq. mi. (550,985 sq. km). Cap.: Paris. 3.… …   Universalium

  • china — /chuy neuh/, n. 1. a translucent ceramic material, biscuit fired at a high temperature, its glaze fired at a low temperature. 2. any porcelain ware. 3. plates, cups, saucers, etc., collectively. 4. figurines made of porcelain or ceramic material …   Universalium

  • China — /chuy neuh/, n. 1. People s Republic of, a country in E Asia. 1,221,591,778; 3,691,502 sq. mi. (9,560,990 sq. km). Cap.: Beijing. 2. Republic of. Also called Nationalist China. a republic consisting mainly of the island of Taiwan off the SE coast …   Universalium

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”